Progress at the construction site of OVO Wrocław – the floors are ready

The works on OVO Wrocław are currently being conducted
OVO Wrocław
All floors have been already concreted in a luxurious investment which is being realized by Wings Properties in Wrocław – from underground tiers to the sixth floor. At present, the works are being conducted inside the building and on the elevation.

There are ca. 300 people working at the construction site of OVO Wrocław. The concrete construction of a multifunctional complex is almost ready. The only thing left is the completion of the roof which is ready in ca. 70 per cent.

 

The works on lower levels are being conducted at the same time as the works on the highest floors. Moreover, the montage of installations and finishing works are currently being conducted in the underground tiers and the partition walls have been already completed. The similar situation is on the ground floor. The bricklayers are constructing the partition walls and mounting the window woodwork on the first floor, which is intended for hotel rooms of DoubleTree by Hilton. Two model rooms which are supposed to host some guests were performed in the middle of the construction site. Furthermore, the partition walls and floors are being realized on the residential floors – that is on the fourth, fifth and sixth floors. We are also conducting some works at the building’s elevation. The sub-construction for Corian is being performed and it will decorate OVO Wrocław and give it a characteristic rounded shape. The sub-construction is ready in 50 per cent – says Paweł Laszecki, engineer of the OVO Wrocław project.

 

The general contractor is Eiffage Polska Budownictwo SA. The works concerning OVO Wrocław are being conducted in so called design & build system. It means that the executive project is being realized simultaneously with construction works but it property exceeds the building. The project’s elevation will be made from Corian – a plastic material which enables giving the building an aerodynamic form. The works are being conducted in accordance with the schedule thanks to which the OVO Wrocław complex will be completed in 2016.

 

The 9-tier complex will reach 25 meters and it will combine many functions such as: apartments, penthouses, offices, service locals, fitness center and hotel. The building’s project was prepared by the Gottesman–Szmelcman Architecture studio and its investor is Wings Properties which is owned by the Star Group Poland developer group.

 